DPTAC: Return to Home  Page
   
 About DPTAC  |  Publications  |  Site Map  |  Links  |  Home 
Green line break

Inclusive projects

9. A guide to best practice

9.1 The strategic definition phase

(1) Project inception and definition.
Preparation of business case.

Key tasks

  • Where relevant, discuss and understand the commercial, legal and moral benefits of high quality access.
  • Understand the whole-life cost benefits of delivering inclusive environments.
  • Integrate these benefits with other business case issues.
  • Where relevant undertake an access audit or other review of existing premises or operations to establish existing strengths and weaknesses and potential future benefits.

Relevant documentation

  • Pre-existing Access Audits and results of user consultation.
  • Other market analysis.

Key participants

  • Employer/developer.
  • End users/occupiers.

Relevant outputs

  • Business case to include Access considerations.

Notes:

  • Access issues (ie the accessibility of existing and proposed premises) are likely to contribute to the business case behind the development. This is particularly relevant for service providers with a high throughput of members of the public.

(2) Appointment of key project team advisors including strategic advisor/ project manager, lead designer and cost consultant.

Key tasks

  • Employer/Developer to locate appropriately skilled personnel to contribute to the definition, design and construction and occupation processes through a process of tender (if required), interview and appointment.
  • Ensure that the basis of the appointments (the consultancy agreements) adequately record in detail the scope of service for each stages for each of the participants, including the access functions listed in this guide.
  • Ensure the financial remuneration is adequate to ensure that appropriate resource is made available by each participant to adequately undertake the duties described in this table.
  • Ensure that this resource is made available on a planned and committed basis.
  • Ensure that the continuity of the personnel contributing to the scheme is maximised.

Relevant documentation

  • Project inception/business case documentation.
  • Consultant's tender documentation.
  • Draft consultancy agreements.

Key participants

  • Employer/ Developer.
  • Lawyer.
  • Access Champion.
  • Project Manager.
  • Lead Designers.

Relevant outputs

  • Signed or sealed consultancy agreements.

Notes:

  • The number of other consultants appointed at this early stage will be dependent on the nature of the scheme.
  • This is ideally the stage at which the Access Champion (whether they be the architect or an independent appointment) is appointed.
  • NB: The appointment (the consultancy agreement) may be limited to the development of the scheme to a particular design stage. For example the existence of the scheme may be dependant on securing a planning consent.

(3) Strategic brief.

Key tasks

Ensure that all key participants fully understand the access requirements of the business case including the legal, moral and commercial drivers within it.

Based on the project inception/business case documentation, discuss and agree the content of the strategic brief in accordance with the advice given in Part III of this guide.

For example this might include on assessment of:

  • Corporate needs and objects.
  • Strategic intent/mission statement.
  • Design aspirations with relevant priorities.
  • Outline design and construction requirements.
  • Client or sector led design standards (such as those provided by the National Health Service).

After completion of any relevant feasibility studies, the strategic brief will also include:

  • An assessment of options including procurement options.
  • Value for money assessments.
  • Project structure.
  • Adaptability/future proofing.

Relevant documentation

  • Project inception/ business case documentation.
  • Consultancy agreements.
  • Feasibility Studies (where these have been undertaken prior to the full completion of the strategic brief).
  • Any pre-existing access policies or standards that the employer or developer might have.
  • Any sector-based access policies that may exist.

Key participants

  • Employer/developer.
  • Access Champion.
  • Lead designer.
  • End user/occupier.
  • Project manager.

Relevant outputs

  • Those sections of the strategic brief that relate to access as described in Part III of this guide.
Notes:
  • It may not be possible to fully complete the strategic brief until after any feasibility studies have been undertaken. This is particularly relevant where multiple sites are being considered.
  • The importance of involving the end users/occupiers during the initial preparation of the Strategic Brief should not be under estimated.

(4) Feasibility studies: (RIBA Stages A&B).

Key tasks

  • Visit site(s) and understand the topography, local transport infrastructure and other relevant issues.
  • Review local Development Plan (DP) and any relevant Supplementary Planning Guidance (SPG) to fully understand planning and other local statutory restrictions.
  • Analyse any access implications of proposed scheme(s) being put forward.
  • Assess any design proposals against the strategic brief and advise on the implications of any shortfall.
  • Advise on alternative methods of delivering access.
  • Develop an understanding of the financial implications of any differing access proposals.
  • Ensure that the access implications of different procurement solutions are fully debated/understood. For example: will subsequent contracts for the fitting out of shell and core areas also be appropriately designed and constructed? If this issue is not addressed, then good intentions can be compromised.

Relevant documentation

  • Architects drawings/specifications.
  • The local DP and SPG where relevant.
  • The strategic brief including design standards.
  • The consultancy agreements.
  • The cost plan.

Key participants

  • Access Champion.
  • Employer/Developer.
  • Lead Designer.
  • Town & Country Planning Advisor.
  • Project Manager.
  • The end users/occupiers.

Relevant outputs

  • Relevant sections of the feasibility report(s) including commentary on how each option addresses the initial elements of the strategic brief as set out in Part III of this guide i.e.:
    • Corporate needs and objectives.
    • Strategic intent/mission statement.
    • Outline design and construction aspirations.

Notes:

  • This stage might precede the strategic brief. Alternatively some elements relating to particular sites might be completed after feasibility studies have been undertaken.
  • The choice of scheme, site and brief will be made following the collection consideration of many issues, not just those relating to access.

9.2 The design and construction phase

(5) Draft design and construction brief.

Key tasks

  • Develop the strategic brief into a draft design and construction brief in accordance with the recommendations made in Part III of this guide.
  • Re-affirm the relevant elements of the Strategic brief ensuring that the relevant elements have been properly considered and integrated into the draft design and construction brief.
  • In developing the strategic brief, ensure that all parties understand the distinction between essential (mandatory) access standards, which are minimum provision, and best practice (aspirational) access standards which contribute to inclusive environments.
  • Establish the financial ramifications (if any) of choosing best practice design standards rather than the statutory minimum standards.
  • Develop designs in accordance with chosen design standards.
  • Define the project structure in respect of the lines of communication, authority and contract all parties.
  • Liaise with the end user/occupier to establish in detail how the building will be used during the operational phase. If necessary and in response to the consultations amend appropriate design standards to reflect the intended use of the building.
  • Where the design and construction brief is to be used as an Employers Requirement Document, specify how the bidder is to demonstrate their compliance with the access requirements of the brief at each stage (i.e. through appointment of their own expert, through illustration, plans, text or presentation).

Relevant documentation

  • Project inception and business case documentation.
  • Consultancy agreements.
  • Feasibility studies.
  • The Strategic Brief.

Key participants

  • Employer/developer.
  • Lead designer.
  • Access Champion.
  • End users/occupiers.

Relevant outputs

  • A draft design and construction brief meeting the requirements made in section III of this guide.

Notes:

  • The exact format and timing of the draft Design and Construction Brief may vary. Whatever the nature of the design and construction brief, it is essential that access is a continuous consideration during the development of the design.
  • This should be ideally completed before outline proposals (RIBA Stage C) are developed and should form the basis of all subsequent design.

(6) Outline proposals (RIBA Stage C).

Key tasks

  • Based on the recommended option at feasibility stage and the standards and requirements set out in the draft Design and Construction brief; develop an outline design proposals.
  • At all stages of the design development review the design against the Strategic Brief and the Draft Design and Construction Brief to ensure that the two are compatible. Any instances where the design does not meet the requirements of the brief should be thoroughly re-assessed.
  • Consider corporate needs and objectives and whether the emerging design is compatible.
  • Re-visit and understand the practical implications of the chosen access standards and the effect they will have on the design.
  • Compare emerging drawing and specification proposals against the chosen design standards and address any shortfalls.
  • Access as a 'desk top exercise' whether the design meets relevant statutory requirements including Building Regulations and Fire Precaution requirements.
  • Similarly assess whether the design meets local town & country planning requirements including the local transport plan, the local Development Plan and any Supplementary Planning Guidance. This will require further development at a subsequent stage.
  • Consider local transport infrastructure requirements.

Relevant documentation

  • The Draft design and construction brief including appropriate design standards.
  • Feasibility report(s).
  • Emerging Stage C drawings and specifications.
  • Local DP/SPG/Transport plan.

Key participants

  • Employer/developer.
  • Lead designer.
  • Access Champion.
  • End users/occupiers.

Relevant outputs

  • A Stage C design that meets the access requirements of the strategic and draft design briefs.
  • Where required, a commentary on the access strategy (for the relevant section of the Stage C report). This will form the basis of any access statement required in connection with the Planning Application.

Notes:

  • The Access Statement will begin to develop as an integral part of the Stage C report, building on the considerations in the strategic brief.
  • Access Statements are increasingly required in connection with planning and funding applications and will be an essential part of the next stage (Stage (7) Initial statutory consultations and outline planning consents.

(7) Initial statutory consultations and where relevant an application for outline planning consent.

Key tasks

  • Based on the strategic and draft design and constructive briefs and the emerging Stage C design:
    • Hold pre-application consultations with local Access Officer (if the local authority has one) and Planning Officer.
    • Liase with Building Control/approved Inspector/Statutory Highways Authority, Fire Authority.
    • Consider and integrate any amendments required to the scheme to meet statutory obligations.
    • Re-consult with statutory authorities based on any issues raised and revisions made.

Relevant documentation

  • The Strategic Brief and the Draft Design and Construction Brief.
  • The Stage C design and specification.
  • Relevant design standards.
  • Statutory documentation including local DP, SPG, Building Regs, Fire Precaution Legislation.
  • The draft Access Statement.

Key participants

  • Local Access Officer/Planning Officer.
  • Building Control/ Approved Inspector as necessary.
  • Statutory Highways Authority.
  • Fire Authority.
  • Lead Designer.
  • Employer/developer.
  • The Access Champion.

Key outputs

  • An amended (if appropriate or necessary) outline design that meets the requirements of both the strategic brief and the draft design and construction brief and any statutory requirements.
  • An Access Statement for incorporation into any planning application.

(8) Appoint remainder of design team.

Key tasks

  • It is essential that the employer/developer properly appraise the access capabilities of any subsequent designers or other team members. The Access Champion should contribute to this process.
  • The manner in which these designers shall demonstrate their ability shall also be considered whether it be through track record, assessment or discussion. This process could be very similar to the method for the appointment of an Access Champion as described in Part IV of this guide.

Relevant documentation

  • The consultancy agreements.

Key participants

  • Employer/developer.
  • Other designers.
  • Lawyers.

Relevant outputs

  • Consultancy agreements containing the required scope of service and the basis of remuneration.

Notes:

  • The nature of the scheme will dictate which designers are appointed in which sequence and at what stage.
  • For example lighting, catering or interior designers may be specialist appointments on larger schemes.
  • The Access Champion will have a key role in ensuring that all participants are properly considering access issues at all stages.
  • Contractor may appoint their own designers. If this does take place it is important to ensure that the 'Designing Contractors' competence also is assessed.

(9 & 12) Scheme design and detailed design stages (RIBA Stages D&E).

Key tasks

  • Based on the Stage C and then D design and the requirements of the Strategic Brief and the Detailed Design and Construction brief, develop an appropriate and corresponding scheme and detailed design.
  • At all stages of the design development review the design against the Briefs to ensure that the two are fully compatible. This is best achieved through a formal review and sign-off process specifically focussed on access requirements.
  • Any designs not fully compatible with the brief should be thoroughly re-assessed and the design amended if necessary.
  • In particular:
    • Consider the access implications of various design options put forward.
    • Hold specific workshops or design team meetings to consider access related issues.
    • Consider whether the design meets relevant statutory obligations including the local DP and SPG, Building Regulations and any outline Planning Conditions.
    • Consider relevant transport infrastructure.
    • Liase with statutory authorities.
    • Revisit the site to understand the site related access implications of the proposed scheme design.
    • Liaise with end user/occupier.
  • If the project is to be tendered at this stage, ensure that the tender documentation is specific about the access design and construction obligations of the contractor.

Relevant documentation

  • The strategic brief.
  • Consultancy agreements.
  • Stage C and D drawings and specifications.
  • Detailed design and construction brief.
  • Local DP/SPG.
  • Relevant design standards.

Key participants

  • Employer/developer.
  • Lead designer.
  • Other designers.
  • Access Champion.
  • Statutory authorities as necessary.
  • End users/occupiers.
  • Local Access groups (on larger schemes).

Relevant outputs

  • A Stage D + E design that meets the requirements of the strategic design and construction brief.
  • An updated Access Statement.

Notes:

  • The exact sequence and format of the scheme and detailed design may vary. The key requirements of both stages are broadly the same, hence the reason that they are displayed here on the same page. Similarly the Design and Construction brief will develop in parallel with these stages.
  • Depending on the chosen procurement route, there may be substantial elements of detailed design that takes place after construction has commenced.
  • In such circumstances it is also possible that the latter stages of design are being undertaken by different designers possibly those appointed by the contractor. In such cases it is important to ensure that Access considerations are fully co-ordinated across all designers. The Access Champion can play a big role in implementing such a strategy.

(10) Detailed design and construction brief.

Key tasks

  • To develop in detail the design and construction requirements in accordance with the recommendations made in Part III of this guide.
  • The exact format and timing may vary, but as a minimum it should address the following:
    • Re-affirm the relevant elements of the Strategic brief and the draft design and construction brief. Ensure that these have been properly considered and integrated.
    • Describe in detail the project structure in respect of the lines of communication, authority and contract between the Access Champion and the remainder of the project team including the contractor and any designer.
    • Provide enhanced details on the specific design aspiration of particular functions or elements of design and construction.
    • Undertake discussions with occupier/end user in respect of how the building will be used post-completion. If necessary amend appropriate design standards to reflect the intended use of the building.
    • Provide details of design standards including the detailing of any prescriptive design requirements where appropriate.
  • Liase with the cost consultant and fully understand the financial ramifications of selected design standards.
  • Where the brief is to be used as an Employers Requirement Document, specify in detail how the bidder is to demonstrate their compliance with the access requirements of the brief at each stage (i.e. through appointment of their own expert, through illustration, plans, text or presentation).

Relevant documentation

  • Project inception and business case document.
  • Consultancy agreement.
  • Feasibility studies.
  • The strategic brief.
  • The draft design and construction brief.
  • The Stage C Designs.
  • Bibliography of design standards.

Key participants

  • The employer/developer.
  • The lead designer.
  • The end users/occupiers.
  • The remaining designers (including the contractor's designers where relevant.
  • The cost consultant.
  • The Access Champion.

Relevant outputs

  • The detailed design and construction brief in accordance with the recommendations made in Part III of this guide.

Notes:

  • The exact timing and format of this brief may vary substantially depending on the requirements of the project and the form or procurement.
  • In some instances this detailed document may form the basis of the access elements of Employers Requirements (when using a D&B route) or Invitation to Negotiate (when using PFI).
  • In such cases the detailed recording of access design and construction standards in essential.

(11) Detailed statutory consents.

Key tasks

  • Undertake further pre-application consultations with relevant statutory authorities including the local Access Officer (if the Local Authority has one).
  • Identify those design elements that are relevant to access.
  • Fully develop the Access Statement for use in the detailed planning application, the Building Regulation consent and any consents required from the statutory Highways Authority.
  • Work with the Fire Consultant/statutory Fire Authority on appropriate means of escape and life protection strategies.
  • Feedback all findings and conclusions to Design Team and assist with integration of these findings into the relevant design.
  • Undertake the detailed applications and secure the statutory consents.

Relevant documentation

  • Stage E design information.
  • DP/SPG.
  • Other Statutory instruments such as the Building Regulations, fire precaution legislation, Highways requirements etc.
  • Appropriate design standards.
  • Strategic Brief and detailed design and construction brief.
  • Draft Access Statements and the Access Strategy defined in the proceeding briefs.

Key participants

  • Employer/developer.
  • The design team.
  • Statutory authorities.
  • The Access Champion.
  • The contractor (where appropriate).
  • Local Access groups (on larger schemes).

Relevant outputs

  • Access statement(s)
  • Statutory consents

Notes:

  • Detailed statutory consents are likely to be granted incrementally when dealing with larger and more complex schemes. This will also be the case with those schemes prepared with significant elements of contractors design. This stage may therefore take place over a prolonged period of time.

(13 & 14) Main contractor appointed. Trade or sub-contractors appointed.

Key tasks

  • Assessment of the suitability, skills, resource and experience of the contractor from an access perspective. (Part IV gives guidance on how this might be achieved through a process of assessment of experience, track record and interviews).
  • In particular, if the contractor has design responsibilities and the Design Team are not to be novated, then the contractors designers skills and competence should be vigorously assessed.
  • If novation is to take place, ensure the basis of appointment to the contract or is similarly robust and that the influence of the Access Champion is not compromised.
  • Ensure the contractor has allocated appropriate resource to effectively deal with access issues.
  • The contract documents should explicitly state the access requirements of the scheme and the contractor's role in delivering them. Enclosing the access elements of the Detailed Design and Construction Brief and any Access Statement will assist in clearly stating these requirements.
  • The contract documents should also state how the contractor(s) are to actively deliver the access requirements of the briefs and of the designs. This could be achieved by requiring the contractor to include a compulsory section on access, in each of his monthly progress reports. These would require him to actively demonstrate how access has been considered in the course of the month.
  • This reporting requirements could be supplemented by a 'tick-sheet' that places the onus of proof on the contractor. For example the tick sheet might ask: Passenger Lift: has the manufacture's design proposals been checked against section 17.46 of the detailed design and construction brief?

Relevant documentation

  • Tender (and subsequently) contract documentation.
  • Access Statements.
  • Detailed Design and Construction briefs.
  • Deeds of Novation.
  • Contractor method statements and access experience.

Key participants

  • Main contractor.
  • Sub contractors.
  • Employer/developer.
  • Lead designer.
  • Access Champion.

Relevant outputs

  • An assessment of the contractor's ability to design and/or construct an appropriately accessible building.
  • Appropriate contract documentation including evidence of professional indemnity insurance where contractor is undertaking elements of design.

Notes:

  • The contractor may be appointed at very early stage in the design process or much later. The presence or absence of contractor's design will significantly influence the appropriate level of design competence required from the contractor.
  • The extent of design undertaken by the contractor will vary enormously. It could consist of the detailed design of the entire project or be limited to particular packages such as lighting, catering or passenger lifts. Alternatively the contractor may have no design responsibilities.
  • The design process itself would then take place in accordance with the recommendations made in RIBA stage D+E above.
  • Where there are substantial elements of contractor's design, setting up and implementing a robust self certification regime for the contractor is essential. Research indicates that access issues are often overlooked during contractor's design and construction.

(15) Construction.

Key tasks

  • Ensure that the contractor's self-certifying reporting and checking regime is implemented in accordance with the requirements of the contract. The Access Champion will play a key role in this task.
  • Monitor construction to ensure appropriate co-ordination between key trades and that the construction takes place in accordance with the requirements of the agreed design.
  • Issue supplementary design advice as necessary in response to change requests or requests for information.
  • Liase with statutory authorities to secure detailed consent/discharge of conditions if appropriate based on contractor's design.

Relevant documentation

  • Contract specification and drawings.
  • Statutory consents.
  • Relevant sections of the contractor's progress reports and check-sheets.

Key participants

  • Contractor.
  • Employer/developer.
  • Access Champion.
  • Lead designer.
  • Other designers.
  • Project manager.
  • End users/occupiers.

Key outputs

  • A completed and considered set of access issues reports and checklists (provided by the contractor and monitored and approved by the Access Champion).

Notes:

  • Ensuring that a project is appropriately designed and specified is an essential step in delivering an accessible building. However in many instances the construction is not undertaken in accordance with the stipulated design standards. This can seriously compromise the quality of the completed building.
  • This happens for a number of reasons including errors in construction, unforeseen circumstances, clashes or the absence of specific and appropriately detailed construction requirements.
  • It is therefore essential that the Access Champion maintains an input during the construction process to overcome these potential problems.

(16) Hand-over.

Key tasks

  • Ensure operating and maintenance manuals contain appropriate information on the operation and maintenance of access related equipment.
  • Ensure that the end users/occupiers are appropriately familiarised with the access strategy for the building and also on any access related equipment.

Relevant documentation

  • Operating and maintenance manuals.
  • Access statements/strategies including a statement of access provisions.
  • As Built Drawings and Specifications for subsequent fit out contracts.
  • Training manuals.

Key participants

  • Employer/developer.
  • Designers.
  • Main contractor.
  • Sub-contractors.
  • Access Champion.

Relevant outputs

  • O&M Manuals.
  • Familiarisation with access related equipment and strategy.

Notes:

  • Often the completion of one contract or project does not mean that the building or environment is complete. Subsequent contracts may be placed for fitting-out certain elements of the building. If this is the case then it is important to ensure that these are similarly well designed and constructed. (Subsequent contracts for the fitting out of shell and core areas can seriously compromise the quality of access if not undertaken appropriately).
  • Hand over may be phased or staged depending on the nature of the development.

9.3 The occupation phase

(17) Occupation.

Key tasks

  • Provide periodic training to occupants on access into and within the building. This should also include issues on building use that are unrelated to the structure and fabric. Training might include:
    • Understanding of access strategy for the building.
    • Familiarity with the facilities within.
    • Disability awareness/customer service.
    • Appropriate staff interface with disabled people.
    • General health and safety issues.
    • Recipients of training should include personnel staff, facilities and building managers, reception staff and any others involved in interfacing with the public.

Relevant documentation

  • Operating and maintenance manuals.
  • Training manual.

Key participants

  • End user/occupier.
  • Local Access Group.
  • Access Champion.

Relevant outputs

  • Training regimes.

Notes:

  • The occupation may be phased or staged depending on the nature of the development.

(18) Occupation brief.

Key tasks

  • Review the briefing, design, construction and occupation processes and feedback lessons learned for subsequent projects.
  • Review the buildings actual performance measured against the original business need, perhaps through an access audit or staff interview.
  • Provide information on how to make adjustments or improvements in the day to day operation of the building.

Relevant documentation

  • The operating and maintenance manuals.
  • As built drawings.
  • Staff feedback based on interviews and observations.

Key participants

  • End user.
  • Employer/developer.
  • Lead designer.
  • Access Champion.

Relevant outputs

  • The Occupational brief.
  • Specification for building and equipment improvements.
  • Specification for continuous staff training.

Notes:

  • The format of the occupational brief will vary. Guidance on the content is given in section III of this guide.

Published: 17 June 2003

[ Previous ] [ Contents ] [ Next ]

Top of page

Green line break

Updated: 12 January 2004 | Copyright disclaimer | Content disclaimer | © Crown copyright 2008